Production orders

Production orders and bills of materials for a UAE manufacturer

Updated

A small UAE manufacturer that assembles or packs products from bought-in materials can record its production in 4softerp.net. You define a one-level recipe, raise a production order, components are consumed from stock at cost, and the finished product is received with a journal entry.

What the production module covers

The module is deliberately simple. A recipe, also called a bill of materials (BOM), lists the components and quantities for one unit of a finished product. It has one level: components are bought or stocked items, not other recipes.

A production order says how many units you are making. Completing it moves stock and posts the accounting entry, so nothing is posted by hand. Components must be in stock at completion, and reservations can hold them for an order.

An example: water coolers assembled in Sharjah

Consider a workshop in the Sharjah industrial area that assembles floor-standing water coolers. One unit needs a steel cabinet, a compressor, a tank, a tap set and a packing carton, all held in its warehouse.

The planner creates an order for 60 coolers. On completion the system takes 60 of each component out of stock at current cost and receives 60 finished coolers. These are then sold like any other product, with a delivery.

How cost is built

The cost of the finished product is the cost of the components consumed. The entry records the consumption of components and the receipt of finished goods, so cost moves from component stock to finished-goods stock and the journal shows both sides.

The costing method of the component warehouse flows through: components held under FIFO are consumed oldest layer first, and the product takes that cost.

Labour and overhead are not added to product cost. If you need them carried in the cost of goods, handle that adjustment outside this module with your accountant.

What this module does not do

There is no automatic planning of what to make or buy, no multi-level assemblies and no lot or serial tracking in production. For a sub-assembly, make it as its own order first and then use it as a component.

  • One-level recipes only.
  • No automatic material planning.
  • No batch or serial numbers in production.
  • No labour or overhead in cost.

Planning around the module in practice

Before you create the first recipe, list the components with their units and check that each exists as a stocked product. A cooler that needs five components needs five product records and five quantities in the warehouse.

After completion, check the journal entry once against your own calculation. Record scrap honestly: a recipe describes the standard quantity, so if real consumption is higher, note the reasons and adjust the recipe at the next review. Product standards and licensing for manufacturing stay with your licensing authority and advisers.

Seasonal demand, for example before the summer peak for cooling products, can be met by raising several production orders ahead of time and using reservations so that sales do not consume components needed for planned runs. Keep finished goods and components in separate warehouses if that helps your team see at a glance what is ready to ship.

Frequently asked questions

Can a recipe contain another recipe?

Not directly. Recipes have one level. Run a production order for the sub-assembly, receive it into stock and then use it as an ordinary component.

Is labour included in the product cost?

No. The cost of a finished product equals the cost of the components consumed. Adjust for labour and overhead outside the system if you need to.

Does the system plan production for me?

No. A planner creates each production order, and the system handles stock consumption, receipt and the accounting entry.