Production orders

Production orders and bills of materials for a Norwegian AS workshop

Updated

A Norwegian workshop that builds steel frames, floats or control cabinets needs to know what each finished item cost in materials. 4softerp.net supports one-level bills of materials and production orders that consume components from stock and receive the finished product with an accounting entry. This guide shows how, and where it stops.

A recipe with one level

A bill of materials, or recipe, lists the components needed for one finished product. Take a mooring frame: eight steel profiles, sixteen bolts and two shackles. Each of those is a product in stock; the frame is the finished product.

The recipe has a single level. A component cannot itself be a recipe with further components inside the same order. If your frame includes a welded sub-assembly, treat the sub-assembly as its own finished product made by its own production order first.

Before you build the first recipe, make sure every component exists as a product with a warehouse and a cost. A recipe that points to a component without stock will produce an order that cannot be completed, and the fix is a goods receipt, not a change to the recipe.

What a production order does

When you run a production order for ten frames, the ERP takes the components out of the chosen warehouse at their current stock cost and receives ten finished frames into stock. An accounting entry moves the value from components to finished goods.

If the order is run against a warehouse that uses FIFO, the oldest layers are consumed first and the finished frames carry that cost. Under weighted average they carry the blended cost. Either way the value that leaves component stock equals the value that enters finished goods stock.

  • Components leave stock at cost
  • Finished goods enter stock
  • An accounting entry is posted for the movement
  • Weighted average or FIFO applies as set for the warehouse

What is not in the cost

The cost of a finished item is the cost of its components. Labour and overhead are not added by the ERP. If your workshop wants hourly cost in the product price, that calculation lives outside the production order today.

There is also no automatic material planning, no multi-level explosion and no batch or serial tracking inside production. Orders are created by people, one at a time.

Many small workshops do not need more than this. The question to ask is whether you need to know material cost per product with reasonable accuracy, and whether people are willing to record each build. If both answers are yes, one-level recipes work well.

Fit for a small Norwegian workshop

This is enough for a workshop that wants to see material cost per finished item and keep the stock correct after each build. It is not a planning system for a factory floor. Keep the statutory valuation of work in progress and finished goods with your accountant under Norwegian accounting rules.

Frequently asked questions

Can a recipe contain another recipe?

No. Bills of materials have a single level. A sub-assembly can be produced first through its own production order and then used as a component in the next one.

Is labour included in the production cost?

No. The cost of a finished product is the cost of the components consumed from stock. Labour and overhead are not added by the production order, so keep any hourly costing outside it.

Does the ERP plan material needs automatically?

No. There is no automatic requirements planning. A person creates each production order and the ERP consumes components from stock when the order is run.